TIMELINES in TG-bPASS

S.No.SERVICESDEPARTMENTTIMELINE
ABuilding Plan
A1Plot size up to 63 square meters/75 sq. yards (residential)MA&UD No Building Permission required
A2Plot size up to 500 square meters and height up to 10 meters (residential)MA&UD Instant
A3Plot size above 500 square meters and height above 10 meters(residential) and all non-residential buildings irrespective of plot size and height of the buildingsMA&UD 21 Days
A3.1
1Raising of shortfall if any MA&UD 10 Days
2Compliance of DC conditions and submission of mortgage from the date of issuanceMA&UD 30 days
3Compliance of DC conditions and submission of mortgage with interest (extra period)MA&UD 30 Days
BNOCs for Building Plan
1NOC for Petrol Bunk, Multiplex & TheatresPolice (Traffic) 10 Days
2Provisional Fire NOCFire Services 14 Days
3NOC FTLIrrigation 10 Days
4NOC FTLRevenue 10 Days
5NOC for water feasibilityHMWSSB 10 Days
6NALA ConversionsRevenue14 Days
7NOC for height clearanceAAI Instant
8NOC for construction NMA Instant
9Third party proof check of structural designsJNTU/Osmania 10 Days
COccupancy Certificate
C.1Residential buildings in plot area up to 200 sqmtrs and height upto 7 mtrs MA&UD Not Required
C.2Residential buildings in plot area above 200 sqmtrsupo 500 sqmtrs and height above 7 mtrs upto 10 mtrsMA&UD Instant
C.3Residential buildings constructed in plots above 500 square meters and height up to 10 mtrs and all non-residential buildingsMA&UD 21 Days
DLand Use Certificate/Land Conversion Certificate
D.1Land Use Certificate as per Master PlanDTCP/ HMDA3 Days
ELayout
E.1Tentative LayoutMA&UD21 Days
E.2Release of Mortgage after issuance of Final LayoutMA&UD21 Days
FValidity of Building Permit
F.1Non-High-Rise BuildingMA&UD3 Years
F.2High-Rise BuildingMA&UD 5 Years
GValidity for the Layout
G.1From the date of tentative approvalMA&UD2 Years