A | Building Plan | | |
A1 | Plot size up to 63 square meters/75 sq. yards (residential) | MA&UD | No Building Permission required |
A2 | Plot size up to 500 square meters and height up to 10 meters (residential) | MA&UD | Instant |
A3 | Plot size above 500 square meters and height above 10 meters(residential) and all non-residential buildings irrespective of plot size and height of the buildings | MA&UD | 21 Days |
A3.1 | | | |
1 | Raising of shortfall if any | MA&UD | 10 Days |
2 | Compliance of DC conditions and submission of mortgage from the date of issuance | MA&UD | 30 days |
3 | Compliance of DC conditions and submission of mortgage with interest (extra period) | MA&UD | 30 Days |
B | NOCs for Building Plan | | |
1 | NOC for Petrol Bunk, Multiplex & Theatres | Police (Traffic) | 10 Days |
2 | Provisional Fire NOC | Fire Services | 14 Days |
3 | NOC FTL | Irrigation | 10 Days |
4 | NOC FTL | Revenue | 10 Days |
5 | NOC for water feasibility | HMWSSB | 10 Days |
6 | NALA Conversions | Revenue | 14 Days |
7 | NOC for height clearance | AAI | Instant |
8 | NOC for construction | NMA | Instant |
9 | Third party proof check of structural designs | JNTU/Osmania | 10 Days |
C | Occupancy Certificate | | |
C.1 | Residential buildings in plot area up to 200 sqmtrs and height upto 7 mtrs | MA&UD | Not Required |
C.2 | Residential buildings in plot area above 200 sqmtrsupo 500 sqmtrs and height above 7 mtrs upto 10 mtrs | MA&UD | Instant |
C.3 | Residential buildings constructed in plots above 500 square meters and height up to 10 mtrs and all non-residential buildings | MA&UD | 21 Days |
D | Land Use Certificate/Land Conversion Certificate | | |
D.1 | Land Use Certificate as per Master Plan | DTCP/ HMDA | 3 Days |
E | Layout | | |
E.1 | Tentative Layout | MA&UD | 21 Days |
E.2 | Release of Mortgage after issuance of Final Layout | MA&UD | 21 Days |
F | Validity of Building Permit | | |
F.1 | Non-High-Rise Building | MA&UD | 3 Years |
F.2 | High-Rise Building | MA&UD | 5 Years |
G | Validity for the Layout | | |
G.1 | From the date of tentative approval | MA&UD | 2 Years |