| A | Building Plan | | |
| A1 | Plot size up to 63 square meters/75 sq. yards (residential) | MA&UD | No Building Permission required |
| A2 | Plot size up to 500 square meters and height up to 10 meters (residential) | MA&UD | Instant |
| A3 | Plot size above 500 square meters and height above 10 meters(residential) and all non-residential buildings irrespective of plot size and height of the buildings | MA&UD | 21 Days |
| A3.1 | | | |
| 1 | Raising of shortfall if any | MA&UD | 10 Days |
| 2 | Compliance of DC conditions and submission of mortgage from the date of issuance | MA&UD | 30 days |
| 3 | Compliance of DC conditions and submission of mortgage with interest (extra period) | MA&UD | 30 Days |
| B | NOCs for Building Plan | | |
| 1 | NOC for Petrol Bunk, Multiplex & Theatres | Police (Traffic) | 10 Days |
| 2 | Provisional Fire NOC | Fire Services | 14 Days |
| 3 | NOC FTL | Irrigation | 10 Days |
| 4 | NOC FTL | Revenue | 10 Days |
| 5 | NOC for water feasibility | HMWSSB | 10 Days |
| 6 | NALA Conversions | Revenue | 14 Days |
| 7 | NOC for height clearance | AAI | Instant |
| 8 | NOC for construction | NMA | Instant |
| 9 | Third party proof check of structural designs | JNTU/Osmania | 10 Days |
| C | Occupancy Certificate | | |
| C.1 | Residential buildings in plot area up to 200 sqmtrs and height upto 7 mtrs | MA&UD | Not Required |
| C.2 | Residential buildings in plot area above 200 sqmtrsupo 500 sqmtrs and height above 7 mtrs upto 10 mtrs | MA&UD | Instant |
| C.3 | Residential buildings constructed in plots above 500 square meters and height up to 10 mtrs and all non-residential buildings | MA&UD | 21 Days |
| D | Land Use Certificate/Land Conversion Certificate | | |
| D.1 | Land Use Certificate as per Master Plan | DTCP/ HMDA | 3 Days |
| E | Layout | | |
| E.1 | Tentative Layout | MA&UD | 21 Days |
| E.2 | Release of Mortgage after issuance of Final Layout | MA&UD | 21 Days |
| F | Validity of Building Permit | | |
| F.1 | Non-High-Rise Building | MA&UD | 3 Years |
| F.2 | High-Rise Building | MA&UD | 5 Years |
| G | Validity for the Layout | | |
| G.1 | From the date of tentative approval | MA&UD | 2 Years |